Collin CountyDFW Construction

Collin FM 2478 project highlights reconstruct existing roadway

Dallas District project data shows reconstruct existing roadway on FM 2478 in Collin County.

TxDOT Project Tracker data shows reconstruct existing roadway tied to FM 2478 in Collin County. The listed limits run from FM 1461 to FM 455. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $136.8M.

  • Limits: FM 1461 to FM 455.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $136.8M.
  • Official project reference: A00207120.
Source: TxDOT Project Tracker
Collin CountyDFW Construction

Collin FM 543 project highlights reconstruct existing roadway

Dallas District project data shows reconstruct existing roadway on FM 543 in Collin County.

TxDOT Project Tracker data shows reconstruct existing roadway tied to FM 543 in Collin County. The listed limits run from CR 125 to Trinity Fall. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $81.5M.

  • Limits: CR 125 to Trinity Fall.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $81.5M.
  • Official project reference: A00207110.
Source: TxDOT Project Tracker
Rockwall CountyDFW Construction

Rockwall FM 35 project highlights reconstruct existing roadway

Dallas District project data shows reconstruct existing roadway on FM 35 in Rockwall County.

TxDOT Project Tracker data shows reconstruct existing roadway tied to FM 35 in Rockwall County. The listed limits run from IH 30 to East of Chestnut Court. The project is currently categorized as "Planning, 10+ years." Estimated construction cost is listed at about $72.8M.

  • Limits: IH 30 to East of Chestnut Court.
  • Phase/status: Planning, 10+ years.
  • Estimated construction cost: about $72.8M.
  • Official project reference: A00207098.
Source: TxDOT Project Tracker
Wise CountyDFW Construction

Wise FM 1658 project highlights bridge replacement

Fort Worth District project data shows bridge replacement on FM 1658 in Wise County.

TxDOT Project Tracker data shows bridge replacement tied to FM 1658 in Wise County. The listed limits run from at Lake Bridgeport Spillway to .. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $10.4M.

  • Limits: at Lake Bridgeport Spillway to ..
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $10.4M.
  • Official project reference: A00195744.
Source: TxDOT Project Tracker
Erath CountyDFW Construction

Erath FM 1188 project highlights bridge replacement

Fort Worth District project data shows bridge replacement on FM 1188 in Erath County.

TxDOT Project Tracker data shows bridge replacement tied to FM 1188 in Erath County. The listed limits run from At Counts Creek Bridge to .. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $5.3M.

  • Limits: At Counts Creek Bridge to ..
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $5.3M.
  • Official project reference: A00195743.
Source: TxDOT Project Tracker
Wise CountyDFW Construction

Wise FM 51 project highlights bridge replacement

Fort Worth District project data shows bridge replacement on FM 51 in Wise County.

TxDOT Project Tracker data shows bridge replacement tied to FM 51 in Wise County. The listed limits run from At Catlett Creek to .. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $4.1M.

  • Limits: At Catlett Creek to ..
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $4.1M.
  • Official project reference: A00195781.
Source: TxDOT Project Tracker
Ellis CountyDFW Construction

Ellis FM 667 project highlights bridge replacement

Dallas District project data shows bridge replacement on FM 667 in Ellis County.

TxDOT Project Tracker data shows bridge replacement tied to FM 667 in Ellis County. The listed limits run from At Hog Creek to .. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $3.3M.

  • Limits: At Hog Creek to ..
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $3.3M.
  • Official project reference: A00194024.
Source: TxDOT Project Tracker
Tarrant CountyDFW Construction

Tarrant BU 287P project highlights bridge maintenance

Fort Worth District project data shows bridge maintenance on BU 287P in Tarrant County.

TxDOT Project Tracker data shows bridge maintenance tied to BU 287P in Tarrant County. The listed limits run from 4th Street to E Bluff Street. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $2.7M.

  • Limits: 4th Street to E Bluff Street.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $2.7M.
  • Official project reference: A00195745.
Source: TxDOT Project Tracker
Ellis CountyDFW Construction

Ellis FM 1181 project highlights bridge replacement

Dallas District project data shows bridge replacement on FM 1181 in Ellis County.

TxDOT Project Tracker data shows bridge replacement tied to FM 1181 in Ellis County. The listed limits run from FM 1181 at Village Creek Relief to .. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $1.3M.

  • Limits: FM 1181 at Village Creek Relief to ..
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $1.3M.
  • Official project reference: A00194141.
Source: TxDOT Project Tracker
Parker CountyDFW Construction

Parker IH 20 project highlights construct ramps

Fort Worth District project data shows construct ramps on IH 20 in Parker County.

TxDOT Project Tracker data shows construct ramps tied to IH 20 in Parker County. The listed limits run from Ranch House Road to FM 1187. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $5.0M.

  • Limits: Ranch House Road to FM 1187.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $5.0M.
  • Official project reference: A00197469.
Source: TxDOT Project Tracker
Ellis CountyDFW Construction

Ellis FM 660 project highlights rehabilitate existing roadway

Dallas District project data shows rehabilitate existing roadway on FM 660 in Ellis County.

TxDOT Project Tracker data shows rehabilitate existing roadway tied to FM 660 in Ellis County. The listed limits run from FM 813 to SH 34. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $16.2M.

  • Limits: FM 813 to SH 34.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $16.2M.
  • Official project reference: A00196134.
Source: TxDOT Project Tracker
Ellis CountyDFW Construction

Ellis FM 813 project highlights rehabilitate existing roadway

Dallas District project data shows rehabilitate existing roadway on FM 813 in Ellis County.

TxDOT Project Tracker data shows rehabilitate existing roadway tied to FM 813 in Ellis County. The listed limits run from BI 45H to FM 660. The project is currently categorized as "Construction begins within 4 years." Estimated construction cost is listed at about $12.1M.

  • Limits: BI 45H to FM 660.
  • Phase/status: Construction begins within 4 years.
  • Estimated construction cost: about $12.1M.
  • Official project reference: A00196236.
Source: TxDOT Project Tracker